Cost structure and interpretation of requirements in UN 38.3 battery pack testing
A comparison of leading test laboratories quoting against one identical specification: prices, cost drivers, lead times and the interpretation of standard requirements for the lithium-ion traction pack LOR‑BP‑16S7P‑R1.




The study at a glance
Key findings of the benchmark
Leading test laboratories quoted one identical test item against the same specification and response template. The results show that a supposedly standardised test scope varies considerably in price, scheduling and technical interpretation.
Significant price variance for the same test item.
Quotes for the complete UN 38.3 pack programme range from €9,000 to €29,000, with a median of €18,000. That is a factor of 3.2.
T.1 to T.5 drive cost, T.7 drives variance.
The T.1 to T.5 test sequence accounts for 60 to 77% of the quoted total. T.7 overcharge shows the highest relative variance, a factor of 4.6 (€1,500 to €6,960).
Inconsistent interpretation of standard requirements.
There are three different assessments of whether IEC 62133-2 applies to an 11.1 kg pack. Most laboratories that addressed the point require cell-level evidence from T.6 and T.8 before issuing a certificate.
Quoted price and project cost diverge.
Flat fees, adapters, witness testing, disposal and dangerous-goods transport are mostly not part of the quoted totals. A reliable comparison has to look at the total cost of testing.
Lead times and test durations lack transparency.
The earliest start dates differ by three calendar weeks, stated durations range from 21 to 39 working days, and they are calculated on different bases.
A standardised request for quotation makes the quotes comparable
Price comparisons for battery testing only hold if the scope is defined the same way for everyone. The test item, the test scope and the response structure were therefore fixed for all laboratories.
Reference test item
| DESIGNATION | LOR-BP-16S7P-R1, traction pack for e-scooters |
| CONFIGURATION | 16S7P, lithium-ion |
| ELECTRICAL | 57.6 V · 33.6 Ah · 1,935 Wh |
| MASS | 11.1 kg, at most 11.8 kg |
| CLASSIFICATION | small rechargeable battery, ≤ 12 kg |
| SAMPLES | 16 packs: 8 for T.1–T.5, 8 for T.7 |
Manufacturer and application are fictitious. Specification LOR-LH-R60-2026-001 defines every technical parameter, so each laboratory quoted on the same basis.
Scope
| UN 38.3, complete pack programme T.1 to T.5 and T.7, half of the samples new and half after 25 cycles, including pre-conditioning and test summary |
| IEC 62133-2, optional only where the laboratory considers it applicable to the test item |
| Not included cell tests T.6 and T.8, UN R136, EN 50604-1, EMC |
| Terms net prices, delivered to the laboratory, protection circuit active, accredited edition stated, deviations listed as assumptions |
Survey
Laboratories are anonymised with fixed letters. The letters reveal neither identity nor ranking.
Participating test laboratories
These laboratories took part with a quote and agreed to be named. Further laboratories took part anonymously. The logos are not linked to any lab letter.



A fictitious traction pack with realistic key data
Manufacturer and pack are invented. Cells, mass, housing and connectors match a typical traction pack for e-scooters. All laboratories quoted on the same drawing and the same data sheet.

Visualisation of the reference test item LOR-BP-16S7P-R1, illustrative.
Dimensions in mm per specification LOR-LH-R60-2026-001. Dashed: M6 mounting points in the base plate, position schematic.
| HOUSING | AlMg3, 3 mm base plate, bolted lid, perimeter seal |
| INGRESS | IP67, connectors mated or with series cap |
| MOUNTING | 4 × M6 on 320 × 150 mm, torque 8 N·m |
| PRESSURE RELIEF | 1 vent membrane on the lid |
| CONNECTORS | separate discharge and charge, on the end face |
| COOLING | none, no coolant |
For vibration and shock the pack is mounted on the table by its four M6 points, and the vent membrane stays uncovered in all tests. If the mass including the test adapter exceeds 12 kg, the pack counts as a large battery and the number of samples changes.
A €20,000 price gap for an identical scope
The lowest quote is 50% of the median, the highest 161%. All quotes refer to the same test item, 16 samples and an identical test scope.
The spread reflects differences in capacity utilisation, equipment and risk assessment between laboratories. For buyers this means a single quote does not indicate the market price. Without a structured comparison, costs can be up to 3.2 times higher.
T.1 to T.5 drive cost, T.7 drives variance
The T.1 to T.5 test sequence accounts for 60 to 77% of the quoted total. The highest relative spread, however, is in the smaller line items, above all T.7 overcharge.
| Line item | Minimum | Median | Maximum | Factor |
|---|---|---|---|---|
| T.1 – T.5 altitude, thermal, vibration, shock, short circuit · 8 packs | €6,500 | €11,733 | €18,300 | 2.8× |
| T.7 overcharge 8 packs, 4 new and 4 after 25 cycles | €1,500 | €2,000 | €6,960 | 4.6× |
| Pre-conditioning 25 cycles on 8 packs | €1,000 | €1,300 | €3,170 | 3.2× |
| Report & test summary test report and 38.3.5 summary | €0 | €570 | €939 | 1.6× |
Some laboratories quote T.1 to T.5 and T.7 as one item across both sample halves, or include the report and test summary in the test price; the factor for that line item only covers separately priced quotes.
Lead times and test durations lack transparency
In many development programmes, test capacity is the critical path. Earliest start dates and test durations differ considerably and are calculated on different bases.
Inconsistent bases
Some quotes state calendar days from goods receipt to report, some the sum of individual line items without parallel test runs, some a total below that sum. Calendar days are converted here to working days at 5/7. The figures only become comparable with a binding schedule.
Start date as a planning factor
As of October 2026, the earliest start dates range from immediate availability through CW 45 to CW 47, and up to CW 50 for staggered test runs. Some quotes offer a start without lead time. At a similar price, an earlier start takes several weeks off the project plan.
One specification, different interpretations
Any deviation from the defined scope had to be stated as an assumption. These assumptions show that laboratories assess identical requirements differently.
| Assumption | Lab A | Lab B | Lab C | Lab D | Lab E |
|---|---|---|---|---|---|
| Accredited to 38.3 Rev. 8 | Yes | Yes | Yes | Yes | Yes |
| Classified as small battery ≤ 12 kg | Yes | Yes, up to 12.0 kg weighed | Yes | Yes | Yes |
| 25 cycles as separate line item | Yes | Yes | Yes | Yes | Yes |
| Protection circuit stays active | Yes | Yes | Yes | Yes | Yes |
| Can be quoted without cell report | No, T.6/T.8 first | Quote yes, certificate no | Yes | Yes | No, T.6/T.8 first |
| Adapter included | Yes | Yes | No, extra (not priced) | Yes | Yes |
| Witness and disposal | extra | extra, witness €248/h | extra | extra | extra |
| Flat fees outside the total | none | project handling €945 | none | none | none |
| IEC 62133-2 for 11.1 kg | not offered | not offered, 6 kg limit | offered €8,000 | offered €9,490 | not applicable |
Most laboratories that addressed the point only issue the pack certificate after passed cell tests T.6 and T.8. Without that evidence, the project needs one more complete test run.
Laboratories disagree on whether the standard applies to an 11.1 kg vehicle pack: some quotes include the test (€8,000 and €9,490), others do not offer it, limit it to 6 kg or consider it not applicable.
Quotes from 2022 and 2023 were spread wider than in 2026
Same line items, different test items: €5,900 to €47,550. The 2026 study, with one test item, ranges from €9,000 to €29,000, so the years are not shown on one axis. Quotes only become comparable once they are calculated for the same test item. This normalisation is part of Cevelar Arc, our cost- and project-optimised delivery of test campaigns.
| Ref. | Year | Test item and scope as quoted | Quote | Normalised | Added |
|---|---|---|---|---|---|
| H1 | 2022 | Pack, 50 V / 50 Ah, 15 kg · T.1–T.5, T.7, report · cycling by customer | €15,240 | €16,540 | + pre-cond. €1,300 ¹ |
| H2 | 2022 | Pack, 25.9 V / 36.3 Ah, approx. 0.9 kWh · T.1–T.5, T.7, report · cycling by customer · certificate €390 extra | €4,600 | €5,900 | + pre-cond. €1,300 ¹ |
| H3 | 2022 | Pack, 55.2 V, 9.5 kg · T.1–T.5, T.7, report · cycling by customer | €7,950 | €9,250 | + pre-cond. €1,300 ¹ |
| H4 | 2023 | Pack, 58.8 V, 17.5 kg · T.1–T.5, T.7, report · cycling by customer | €10,500 | €11,800 | + pre-cond. €1,300 ¹ |
| H5 | 2022 | Pack, 4 samples, data not stated · T.1–T.5, handling, report · without T.7 | €24,730 | €32,530 | + pre-cond. as quoted €5,800; T.7 €2,000 ¹ |
| H6 | 2022 | Pack 18S10P, 75.6 V, 20 kg · T.1–T.5 incl. report, T.7 | €29,610 | €47,550 | + pre-cond. as quoted €17,940 |
| H7 | 2023 | HV module, 50.4 V, 37 kg · T.1–T.5 incl. pre-conditioning and disposal · without T.7 | €36,500 | n/a | test item class not comparable |
| H8 | 2023 | Pack, 55.2 V, 497 Wh, 9.5 kg · IEC 62133-2 together with UN 38.3 test cycle | €22,130 | n/a | UN 38.3 not priced separately |
| H9 | 2023 | Pack, 50.4 V, 2.4 kWh, 17.5 kg · T.5 short circuit only, 1 sample | €1,435 | n/a | single test |
¹ Added at the 2026 study median for this line item. Other additions are taken from the respective quote.
Normalised to the study scope, the 2022 and 2023 quotes had a median of €14,170, 21% below the 2026 median of €18,000, with a much wider spread. This does not show a price trend, because mass, sample count and test scope of those test items differ. The figures do work as a budget range for similar packs.
A structured comparison cuts the expected price by 50%
A buyer who requests a single quote pays the market average on expectation. Every additional comparable quote lowers the expected best price. The calculation uses every combination of the quotes in this study, all for an identical scope.
Expected best price by number of quotes requested
The saving only applies if every laboratory quotes the same test item with the same number of samples and states its assumptions, as in this study. Otherwise you compare different services. The calculation assumes the contract goes to the lowest quote.
This comparison for your test programme
Cevelar Arc sends one consistent request for your test item to several accredited laboratories, compares the quotes on total cost of testing and schedule, and runs the test campaign through to the report. Optimised for cost and project, with one point of contact. cevelar.com/arc
Planning figures for UN 38.3 pack testing in 2026
Reference values for budget and schedule of a traction pack ≤ 12 kg, derived from the quotes in this study. Stated per pack and per sample so they transfer to your own programme.
| Planning item | Basis | Median | Range |
|---|---|---|---|
| T.1 – T.5 test sequence | per pack | €1,467 | €812 – €2,288 |
| T.7 overcharge | per pack | €250 | €188 – €870 |
| Pre-conditioning, 25 cycles | per pack | €162 | €125 – €396 |
| Report and test summary | per programme | €570 | included – €939 |
| UN 38.3 programme, total | per sample | €1,125 | €562 – €1,812 |
| IEC 62133-2, 11.1 kg pack | per programme, where offered | €8,745 | €8,000 – €9,490 |
| Test duration | working days | 32 WD | 21 – 39 WD |
Schedule from request to test report
In the quote that states an hourly rate, the project flat fee and one day of witness testing add 21% (€2,929). Disposal, dangerous-goods transport and missing cell evidence are charged on top but usually have no price in the quote. Ask for these items before awarding the contract.
All samples must be available at the start of testing, and the T.6 / T.8 cell evidence often earlier. A missing cell report adds one complete test run to the programme.
Total cost of testing, not the quoted price
The quoted totals are consistent in themselves. Actual project costs are usually higher, because significant cost items sit outside the quoted total or are not priced.
Cost items outside the quoted total
| Project flat fees | occasionally, €945, listed separately |
| Adapters and mating connectors | occasionally extra, not priced |
| Witness testing | The client or an appointed expert attends the test at the laboratory. Not included in any quote, occasionally with an hourly rate (€248/h) |
| Disposal | not included in any quote, charged by weight or effort |
| Dangerous-goods transport | delivery and return never included in the test price |
| Cell evidence T.6 / T.8 | required for the certificate by most laboratories |
| 16 samples | built and supplied by the customer |
Checks before awarding the contract
One definition of the test item. Are mass, classification, charge parameters and fixture specified identically for all bidders?
Cell evidence. Are T.6 and T.8 cell-level results available?
Complete costs. Are flat fees, adapters, witness testing, disposal and transport priced?
Schedule basis. Is the duration stated in calendar days from goods receipt or as the sum of individual line items?
Scope of standards. Is it clear whether additional standards such as IEC 62133-2 apply in the target market?
One point of contact from request to test report
This study shows what a consistent request for quotation delivers: comparable quotes within 16 days, price differences of up to a factor of 3.2 made visible, and additional costs, schedules and interpretation of standards laid open. Cevelar does exactly this for your test programme.
Test plan
mandatory tests from specification and standard, before requesting quotes
Request for quotation
one test item, one specification, one response structure
Comparison
total cost of testing, schedule and interpretation of standards
Booking and logistics
samples and slots, in parallel rather than one after another
Evidence
one report; testing and certificate by the accredited laboratory
Do you have a quote for UN 38.3?
We will place it against this benchmark, free of obligation: price per line item, additional costs outside the total, schedule and interpretation of standards. You will know where your quote stands in the market and which questions are worth asking. [email protected]
Cevelar Arc
Cevelar Arc delivers test campaigns optimised for cost and project: from specification through test plan and request for quotation to booking, sample logistics and one joint report. The contract goes to the laboratory that fits the test item, the schedule and the total cost. cevelar.com/arc

[email protected]

[email protected]
